How to check DP series diaphragm pumps after long-term shutdown?
DP series diaphragm pumps require systematic inspection after long-term storage to ensure proper performance restoration.
First check electrical connections and power supply voltage (12V/24V/220V) with multimeter. Clean oxidized terminals with alcohol if necessary.
For flow reduction issues, disassemble pump head to inspect diaphragm elasticity and clean valve balls/seats with ultrasonic cleaner. Replace diaphragms stored over 2 years.
Address leaks by replacing all O-rings and lapping sealing surfaces with 800-grit sandpaper. Apply silicone grease during reassembly.
Abnormal noise indicates bearing lubrication issues - inject Molykote EM-50L grease through motor shaft port and check mechanical clearances.
Final performance test includes 30-minute no-load run (temperature rise ≤35℃), self-priming height test (90% of new pump standard) and flow curve measurement.